Status: in_progress
Portland
|
PROJECT OVERVIEW
|
| NAME OF PROJECT:
|
Banga Ridge Water Supply |
| LOCATION OF PROJECT:
|
Portland |
| SCOPE OF PROJECT:
|
- Phase One: Rehabilitation of the Rain Water Catchment Tank
- Phase Two: Repair sections of the distribution & Transmission pipeline
- Phase Three: Construction of a new intake to increase the volume of water available to supply the community of Banga Ridge & it’s surrounding communities, to include the installation of a new transmission pipeline.
- Phase Four: To Rehabilitate the old source to proper channel the raw water to the intake, Investigate transmission and distribution pipeline to identify all/most leaks and blockages along the pipeline to fix all if not most leaks and create a full report on the status of the pipeline
|
|
ACTUAL COST:
|
$34,684,297.46M
|
|
POPULATION:
|
750 |